The Identify Risk process determines the risks that affect the project and document their
characteristics. Why should the project team members be involved in the Identify Risk process?

A.
They are the individuals that will need a sense of ownership and responsibility for the risk
events.
B.
They are the individuals that will have the best responses for identified risks events within the
project.
C.
They are the individuals that are most affected by the risk events.
D.
They are the individuals that will most likely cause and respond to the risk events.