Which statement best describes quality control for a project within your program?

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality control is a management-driven effort to plan the work properly so the work is done according to plan.

B.
Quality control is an inspection-driven process to keep mistakes out of the customers’ hands.

C.
Quality control is a management-driven policy to do the work correctly the first time.

D.
Quality control is an inspection-driven process to prove the existence of the requirements.