which program process are you working on?

[tagged]
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program.
During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

PrepAway - Latest Free Exam Questions & Answers

A.
Monitor and Control Program Scope

B.
Monitor and Control Program Schedule

C.
Monitor and Control Project Performance

D.
Manage Program Issues