What component of the change management system is responsible for evaluating, testing, and documenting changes

[tagged]
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Management Information System

B.
Integrated Change Control

C.
Scope Verification

D.
Configuration Management System