What should a program manager do when a scope change has been approved that will drastically affect the progra

What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

PrepAway - Latest Free Exam Questions & Answers

A.
Adjust the cost baseline

B.
Communicate cost of the change to all stakeholders

C.
Adjust the quality baseline

D.
Communicate the change to all stakeholders