Which one of the following is not an output of the direct and manage program execution process?

[tagged]
Which one of the following is not an output of the direct and manage program execution process?

PrepAway - Latest Free Exam Questions & Answers

A.
Results of program work

B.
Program budget

C.
Change requests

D.
Request to terminate the program