Which of the following individual should respond to the risk with the preplanned risk response?

[tagged]
Which of the following individual should respond to the risk with the preplanned risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Key stakeholder

B.
Project manager

C.
Risk owner

D.
Project sponsor