Which one of the following is NOT an output of the risk response planning?

[tagged]
You are the project manager of the NHH project for your company. You have completed the first
round of risk management planning and have created four outputs of the risk response planning
process. Which one of the following is NOT an output of the risk response planning?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk register updates

B.
Organizational process assets updates

C.
Project document updates

D.
Risk-related contract decisions