Which one of the following is NOT an output of the process?

[tagged]
There are five outputs of the risk monitoring and controlling process. Which one of the following is
NOT an output of the process?

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assetsupdates

B.
Risk register updates

C.
Vendor contracts

D.
Change requests