You are the project manager of the GHY project for your organization. You are working with your
project team to begin identifying risks for the project. As part of your preparation for identifying the
risks within the project you will need eleven inputs for the process. Which one of the following is
NOT an input to the risk identification process?

A.
Quality management plan
B.
Cost management plan
C.
Stakeholder register
D.
Procurement management plan