Rachel is the project manager of the KJH Project for her company. She needs a method to create
a quick and simple approach to risk identification to communicate the project risk with the
stakeholders. Which one of the following approaches to risk identification should Rachel choose to
provide a quick and simple listing of the project risks?

A.
Delphi Technique
B.
Checklist analysis
C.
Assumptions analysis
D.
Brainstorming