You are the project manager of a new project in your organization. You and the project team have
identified the project risks, completed risk analysis, and are planning the most appropriate risk
responses. Which of the following tools is most effective to choose the most appropriate risk
response?

A.
Cause-and-effect diagrams
B.
Project network diagrams
C.
Delphi Technique
D.
Decision tree analysis