Which of the following strategies will you use to tackle the risk?

[tagged]
You work as the project manager for BlueWell Inc. You are monitoring the project performance.
You want to make a decision to change the project plan to eliminate a risk in order to protect the
project objectives. Which of the following strategies will you use to tackle the risk?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk mitigation

B.
Risk avoidance

C.
Risk acceptance

D.
Risk transference