PrepAway - Latest Free Exam Questions & Answers

Which of the following shows the ratio between a task’s budgeted and actual costs?

[tagged]
Which of the following shows the ratio between a task’s budgeted and actual costs?

PrepAway - Latest Free Exam Questions & Answers

A.
To-Complete Performance Index (TCPI)

B.
Schedule Variance (SV)

C.
Schedule Performance Index (SPI)

D.
Cost Performance Index (CPI)


Leave a Reply