Which of the following processes must be repeated after Plan Risk Responses, as well as part of the Monitor an

[tagged]
Which of the following processes must be repeated after Plan Risk Responses, as well as part of
the Monitor and Control Risks, to determine if the overall project risk has been satisfactorily
decreased?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Limitation

B.
Perform Qualitative Risk Analysis

C.
Identify Risk

D.
Perform Quantitative Risk Analysis