[tagged]
Which of the following processes is described in the statement below? “This is the process of
numerically analyzing the effect of identified risks on overall project objectives.”

A.
Identify Risks
B.
Perform Quantitative Risk Analysis
C.
Monitor and Control Risks
D.
Perform Qualitative Risk Analysis