You are project manager for ABD project. You, with your team, are working on the following
activities:
Probabilistic analysis of a project.
Probability of achieving cost and time objectives.
Trends in Qualitative Risk Analysis results.
On which of the following processes are you working on?

A.
Plan Risk Management
B.
Perform Quantitative Risk Analysis
C.
Perform Qualitative Risk Analysis
D.
Identify Risks