Which of the following plans should a project manager implement if a selected risk strategy fails to be fully

[tagged]
Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

PrepAway - Latest Free Exam Questions & Answers

A.
Fallback plan

B.
Risk response plan

C.
Mitigation management plan

D.
Mitigation plan