Which of the following is NOT an example of a cause for a project risk?

You are the project manager of the HQQ Project for your company. You are working with your
project stakeholders to discuss the risks in the project that can adversely affect the project
objectives. You are discussing the possibilities of causes for an identified risk event in your project.
Your stakeholder is confused on the difference between causes and risk events. Which of the
following is NOT an example of a cause for a project risk?

PrepAway - Latest Free Exam Questions & Answers

A.
Limited team members to complete the project work

B.
Quality assurance programs within the company

C.
Work permit requirements

D.
Schedule constraints on the project