Which of the following is not a component of a risk management meeting?

[tagged]
You are the project manager for Genpact Inc. You have established quarterly risk management
meetings. Which of the following is not a component of a risk management meeting?

PrepAway - Latest Free Exam Questions & Answers

A.
Assessing the overall status of risks in the project

B.
Review of risk responses

C.
Assessment or risk

D.
The availability of the individual