Which of the following components ensures that risks are examined for all new proposed change requests in the

[tagged]
Which of the following components ensures that risks are examined for all new proposed change
requests in the change control system?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk monitoring and control

B.
Scope change control

C.
Integrated change control

D.
Configuration management