Jeff works as a project manager for BlueWell Inc. He is determining which risks can affect the
project. Which of the following are the inputs to the identify risks process that Jeff will use to
accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

A.
Scope baseline
B.
Activity cost estimates
C.
Risk register
D.
Risk management plan