Don is the project manager of the PFO project for his organization. Don is working with the project
team members and two subject matter experts to assess the identified risk events in the project.
Which of the following approaches is the best to assess the risk events in the project?

A.
Determination of the true cost of the risk event
B.
Probability and Impact Matrix
C.
Root cause analysis
D.
Interviews or meetings