[tagged]
Yolanda is the project manager of a high-profile project for her organization. This project has 124
stakeholders from across the organization and many of the stakeholders have high demands and
expectations for the project. Yolanda will need several pieces of project information as she begins
to communicate and manage the stakeholder expectations. Which of the following inputs of the
manage stakeholder expectations process directly addresses the risks that could affect the project
and which must be communicated to the project stakeholders?

A.
Change log
B.
Low-level riskswatchlist
C.
Issue log
D.
Stakeholder register