Where should you document this information for issue resolution?

[tagged]
You are the project manager of the NHQ Project for your company. You are discussing some of
the project issues that need to be resolved in the project. You and the project stakeholders come

to an agreement about the risk issues and how they will be resolved. Where should you document
this information for issue resolution?

PrepAway - Latest Free Exam Questions & Answers

A.
Project management plan for execution

B.
Lessons learned documentation

C.
Issue log

D.
Risk response plan