You are completing the qualitative risk analysis process with your project team and are relying on
the risk management plan to help you determine the budget, schedule for risk management, and
risk categories. You discover that the risk categories have not been created. When should the risk
categories have been created?

A.
Create work breakdown structure process
B.
Plan risk management process
C.
Risk identification process
D.
Define scope process