what type of risk response?

Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to
last 14 months and has a budget at completion of $4,555,000. Tracy’s organization will receive a
bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that
there are several opportunities within the project to save on time by crashing the project work.
Crashing the project is what type of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Transference

B.
Mitigation

C.
Exploit

D.
Enhance