You are the project manager for your organization. You have determined that an activity is too
dangerous to complete internally so you hire licensed contractor to complete the work. The
contractor, however, may not complete the assigned work on time which could cause delays in
subsequent work beginning. This is an example of what type of risk event?

A.
Internal
B.
Secondary risk
C.
Pure risk
D.
Transference