You are the project manager for BlueWell Inc. Your current project is a high priority and high
profile project within your organization. You want to identify the project stakeholders that will have
the most power in relation to their interest on your project. This will help you plan for project risks,
stakeholder management, and ongoing communication with the key stakeholders in your project.
In this process of stakeholder analysis, what type of a grid or model should you create based on
these conditions?

A.
Stakeholder power/interest grid
B.
Influence/impact grid
C.
Salience model
D.
Stakeholder register