Joan is the project manager of the KYU project for her company. She is working with management
on defining a contingency reserve for her project. Currently the project is scheduled to last 18
months and it has a cost budget of $2.5 million. What two areas of the project can the contingency
reserve address in regard to risk management?

A.
Quality and costs
B.
Cost and resource management
C.
Risk and project planning
D.
Costs and schedule