What term is assigned to the low-level of stakeholder tolerance in this project?

[tagged]
You are the project manager of the NKJ Project for your company. The project’s success or failure
will have a significant impact on your organization’s profitability for the coming year. Management
has asked you to identify the risk events and communicate the event’s probability and impact as
early as possible in the project. Management wants to avoid risk events and needs to analyze the
cost-benefits of each risk event in this project. What term is assigned to the low-level of
stakeholder tolerance in this project?

PrepAway - Latest Free Exam Questions & Answers

A.
Mitigation-ready project management

B.
Risk utility function

C.
Risk avoidance

D.
Risk-reward mentality

One Comment on “What term is assigned to the low-level of stakeholder tolerance in this project?

  1. PETER EMUH says:

    LIKE I TOLD YOU BEFORE, PLEASE DONT FORGET TO ALERT ME OF THE NEXT PMI-SP TRAINING YOU SAID WILL KICK OFF AT THE END OF JUNE BECAUSE I WANT TO USE THE CONTACT HOURS FOR MY PMI-SP EXAM AND ALSO TO BOOST MY PMP PDU.
    THANKS.




    0



    0

Leave a Reply