A high-profile, high-priority project within your organization is being created. Management wants
you to pay special attention to the project risks and do all that you can to ensure that all of the
risks are identified early in the project. Management has to ensure that this project succeeds.
Management’s risk aversion in this project is associated with what term?

A.
Quantitative risk analysis
B.
Risk conscience
C.
Risk mitigation
D.
Utility function