You are the project manager of the AFD project for your company. You are working with the
project team to reassess existing risk events and to identify risk events that have not happened
and whose relevancy to the project has passed. What should you do with these events that have
not happened and would not happen now in the project?

A.
Add the risks to the risk register
B.
Add the risks to a low-prioritywatchlist
C.
Close the outdated risks
D.
Add the risk to the issues log