PrepAway - Latest Free Exam Questions & Answers

What risk response is this?

You are the project manager of the YHG project for your company. Within the project, you and the
project team have identified a risk event that could have a financial impact on the project of
$450,000. This risk event has a 70 percent chance of occurring in the project. The project
identifies a solution that will reduce the probability of the risk event to ten percent, but it will cost
$260,000 to implement. Management agrees with the solution and asks that you include the risk
response in the project plan. What risk response is this?

PrepAway - Latest Free Exam Questions & Answers

A.
This is mitigation because the response reduces the probability.

B.
This is not a risk response, but a change request.

C.
This is transference because of the $260,000 cost of the solution.

D.
This is avoidance because the risk response caused the project plan to be changed.


Leave a Reply