Holly is the project manager of the GHH Project. During risk identification and the subsequent risk
analysis process she has identified a risk with a high probability and high impact for her project.
She and the stakeholder agree that the project management plan should be changed to eliminate
the risk threat entirely. What risk response has Holly used in this instance?

A.
This is the risk mitigation response.
B.
This is the avoidance risk response.
C.
This is the transference risk response.
D.
This is a scope change and not a risk response.