PrepAway - Latest Free Exam Questions & Answers

What project management technique are you performing with the project manager in this scenario?

You are interviewing members of a project team to test their understanding of the assigned risk
responses as risk owners. You and the project manager are working together to evaluate the risk
responses to determine their effectiveness in the project. What project management technique are
you performing with the project manager in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk audits

B.
Stakeholder analysis as the project team is a stakeholder

C.
Risk identification with the project team

D.
Risk analysis


Leave a Reply