You are the project manager of the HJU project for your company. This project will last for 18
months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a
scope change request that will likely have an impact on the project costs and schedule. Robert
assures you that he will pay for the extra time and costs associated with the risk event. You tell
Robert that the change request may affect more areas of the project than just time and cost and
that you are worried about the additional risks the change request will bring. What project
management component is responsible for evaluating a change request and its impact on all of
the project management knowledge areas?

A.
Project change control system
B.
Integrated change control
C.
Risk analysis
D.
Configuration management