[tagged]
You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

A.
Resource management plan
B.
Transition plan
C.
Communications management plan
D.
Benefits management plan