Fred is the project manager of the CPS project. He is working with his project team to prioritize the
identified risks within the CPS project. He and the team are prioritizing risks for further analysis or
action by assessing and combining the risks probability of occurrence and impact. What process is
Fred completing?

A.
Risk identification
B.
Perform qualitative analysis
C.
Perform quantitative analysis
D.
Risk Breakdown Structure creation