You are the project manager of a large, high-profile project in your organization. You have realized
that politics within your company may affect the true identification of risk events within the project.
You decide that you’d like to use a method to identify risk events through an anonymous process.
Which one of the following risk events will allow you to collect and distribute risk information
without the stakeholders knowing what other stakeholders are communicating about the project
risk events?

PrepAway - Latest Free Exam Questions & Answers

A.
Surveys

B.
Monte Carlo Technique

C.
Checklist analysis

D.
Delphi Technique