PrepAway - Latest Free Exam Questions & Answers

What is this risk response called?

You are the project manager for the NHQ Project. This project requires that you install 140 copies
of design software onto your department’s computers. The vendor offers you a twenty percent
discount on the software if your company will purchase 150 or more copies of the software. You
communicate this offer with other departments in your firm to see if anyone else would need 10
copies of the software to save your project a significant amount of funds. What is this risk
response called?

PrepAway - Latest Free Exam Questions & Answers

A.
Exploiting

B.
Avoidance

C.
Sharing

D.
Transference


Leave a Reply