What is the sensitivity analysis?

Joyce is the project manager for her company. Joyce and her project team are working through
the quantitative analysis for certain risk events within her project. According to the enterprise
environmental factors the project manager is to perform sensitivity analysis on any risk with an
impact greater than $5,000 in the project. What is the sensitivity analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
It determines which risk events have the most potential impact on the project.

B.
It uses round of anonymous surveys to predict which events are most likely to happen.

C.
It uses rounds of anonymous surveys to predict probability and impact.

D.
It determines possible combinations of risk events to predict overall project success, failure, or
probability of achieving project objectives.


Leave a Reply