What is the project’s cost performance index?

Mark works as a project manager of the NNH project. In this project, he has created a contingency
response that the cost performance index should be less than 0.91. The NHH project has a budget
at completion of $950,000 and is 43 percent complete – though the project should be 50 percent
complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is
the project’s cost performance index?

PrepAway - Latest Free Exam Questions & Answers

A.
0.95

B.
0.80

C.
0.87

D.
0.91