PrepAway - Latest Free Exam Questions & Answers

What is the project’s cost performance index?

You are the project manager of the NNH project. In this project you have created a contingency
response that the cost performance index should be less than 0.93. The NHH project has a budget
at completion of $945,000 and is 45 percent complete – though the project should be 49 percent
complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is
the project’s cost performance index?

PrepAway - Latest Free Exam Questions & Answers

A.
1.06

B.
0.92

C.
-$30,647

D.
0.93


Leave a Reply