Beth is the project manager of the BFG Project for her company. In this project Beth has decided
to create a contingency response based on the performance of the project schedule. If the project
schedule variance is greater than $10,000 the contingency plan will be implemented. What is the
formula for the schedule variance?

A.
SV=EV/PV
B.
SV=PV-EV
C.
SV=EV/AC
D.
SV=EV-PV