You are the project manager of the NJJ project. Your enterprise environmental factors require that
you establish certain risk management rules regarding low risks within your project. What is the
best policy for risks with low probability and low impact in the project management?

A.
These risks should be accepted.
B.
These risks should be placed on awatchlist for future monitoring.
C.
These risks should be identified, but dismissed.
D.
These risks should be placed in the risk register.