You are the project manager of the NGH project for your organization. You want to create a
causeand- effect diagram to help discover the root causes of the risks within the project. Harold,
the CIO, recommends that you create an Ishikawa diagram instead. What is an Ishikawa diagram?

A.
It is a graphical representation of situations showing causal influences.
B.
It is the same thing as a root cause diagram.
C.
It shows how various elements of a system interrelate.
D.
It diagrams the risks according to the work breakdown structure including resources.