Your organization has a project that is expected to last 20 months but the customer would really
like the project completed in 18 months. You have worked on similar projects in the past and
believe that you could fast track the project and reach the 18 month deadline. What increases
when you fast track a project?

A.
Resources
B.
Costs
C.
Communication
D.
Risks