You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

A.
Life cycle costing estimates
B.
Lessons learned documentation
C.
Operational transfer plan
D.
Program closure reports