Frank is the project manager of the NHL Project for his company and he is starting the risk
identification process for the project. Frank needs to ensure that the correct stakeholders are
interviewed as part of risk identification. What document will help Frank to communicate and solicit
inputs of the project stakeholders during risk identification?

PrepAway - Latest Free Exam Questions & Answers

A.
Project charter

B.
Risk register

C.
Requirements management plan

D.
Stakeholder register